CAPITAL PROJECT REQUEST - FIVE YEAR CIP
>$25,000
FORM F-300 - PROJECTS
DEPT / FUND:
042 - Water & Sewer Revenue Fund
PROGRAM: 8600 - Projects
PROJECT NAME: Sewer / Lift Station Control Panels
PROJECT STATUS: Multi-year in Progress
ACCT1#:
ACCT2#:
ACCT3#:
042-8600-535-66-50
PROJECT DESCRIPTION AND JUSTIFICATION:
ADDITIONS / CHANGES JUSTIFICATION
This is an ongoing program to update and replace
declining lift station control panels. Replacement will
ensure continued operability at lift stations by limiting
possible sanitary sewer overflows, keeping the system in
compliance with FDEP.
PURPOSE OF PROJECT:
X
Extend life of existing infrastructure
X
Replace existing infrastructure
Capital improvements
Strategic plan /comp plan
Expand infrastructure
ESTIMATED COST BY YEAR:
Curr. Year
FY 25/26
Land Acquisition
Planning
Design
Architecture/Engineering
Site Devel./Construction
Equipment
Contingency
Other
Project Additions/Changes
TOTAL
PRIORITY:
X Risk
Return on Investment
X Service Level Maint.
Service Level Impro
-
FY 26/27
FY 27/28
-
FY 28/29
-
FY 29/30
-
FY 30/31
-
5 YR TOTAL
-
-
50,000
50,000
50,000
50,000
50,000
50,000
50,000
50,000
50,000
50,000
250,000
250,000
Safety concern, hazardous condition, compliance, non-functional, etc
Highly visible, benefit outweighs cost, economic development potential
Maintains City desired level of service
New or improved service to meet demand
IMPACT ON ANNUAL
OPERATING BUDGET:
Curr. Year
Utility Costs
Maintenance Costs
PROPOSED FUNDING SOURCE(S):
1) 042 - Water & Sewer Revenue Fund
2)
3)
FY 26/27
FY 27/28
-
FY 28/29
-
FY 29/30
FY 30/31
5 YR TOTAL
STRATEGIC PRIORITY, if applicable
LOCATION:
Various
POTENTIAL GRANT FUNDING SOURCE IF APPLICABLE: (List source and matching requirements)
PROJECT LEAD NAME & CONTACT INFO (ADDITIONAL PROJECT INFO AS NEEDED)
Greg Dobbins - PW Director