CIP 2027-2031 (Final) - Flipbook - Page 169
PROPOSED 5 YEAR CIP - 1ST READING
JULY 16, 2026
CITY OF EUSTIS
CAPITAL PROJECT REQUEST - FIVE YEAR CIP
>$25,000
FORM F-300 - PROJECTS
DEPT / FUND:
042 - Water & Sewer Revenue Fund
PROGRAM: 8600 - Projects
PROJECT NAME: Water / Magnolia Ave. Galv. Main
PROJECT STATUS: Future year
ACCT1#:
ACCT2#:
ACCT3#:
042-8600-533-66-02
PROJECT DESCRIPTION AND JUSTIFICATION:
ADDITIONS / CHANGES JUSTIFICATION
Replace approx. 2300' of 2" galvanized water main with
6" PVC between Mary and Kensington. Add fire
hydrants, improve the quality and volume of water per
the galvanized pipe replacement plan. The construction
will be open trench and directional bore.
PURPOSE OF PROJECT:
X
Extend life of existing infrastructure
Replace existing infrastructure
Expand infrastructure
Capital improvements
Strategic plan /comp plan
ESTIMATED COST BY YEAR:
Curr. Year
FY 25/26
Land Acquisition
Planning
Design
Architecture/Engineering
Site Devel./Construction
Equipment
Contingency
Other
Project Additions/Changes
TOTAL
PRIORITY:
Risk
Return on Investment
X Service Level Maint.
X Service Level Impro
FY 26/27
-
FY 27/28
-
FY 28/29
-
FY 29/30
100,000
100,000
FY 30/31
-
5 YR TOTAL
-
500,000
500,000
100,000
500,000
600,000
Safety concern, hazardous condition, compliance, non-functional, etc
Highly visible, benefit outweighs cost, economic development potential
Maintains City desired level of service
New or improved service to meet demand
IMPACT ON ANNUAL
Curr. Year
OPERATING BUDGET:
Utility Costs
Maintenance Costs
PROPOSED FUNDING SOURCE(S):
1) 042 - Water & Sewer Revenue Fund
2)
3)
FY 26/27
FY 27/28
-
FY 28/29
-
FY 29/30
FY 30/31
5 YR TOTAL
STRATEGIC PRIORITY, if applicable
LOCATION:
Magnolia Avenue
POTENTIAL GRANT FUNDING SOURCE IF APPLICABLE: (List source and matching requirements)
PROJECT LEAD NAME & CONTACT INFO (ADDITIONAL PROJECT INFO AS NEEDED)
Greg Dobbins - PW Director
158 of 186
-