PROJECT NAME: Parking Garage
PROJECT DESCRIPTION AND JUSTIFICATION:
Design Build delivery of a 266 space ground plus 2 deck parking
garage $6.9M with brick façade $250k (if desired) and fire
sprinkler $250k (if required).
Site Development / Construction
TOTAL
PROJECT ADDITIONS / CHANGES
New project per Commission request.
Unfunded
7,400,000
7,400,000
CITY OF EUSTIS
UNFUNDED CAPITAL PROJECTS
PROJECT NAME: SR19 FDOT Landscape Maint.
PROJECT DESCRIPTION AND JUSTIFICATION:
The City's share of possible agreement with FDOT to maintain the
SR19 corridor to a higher standard.
Equipment, Vehicles, Etc.
TOTAL
PROJECT ADDITIONS / CHANGES
Annually recurring.
Unfunded
150,000
150,000
CITY OF EUSTIS
UNFUNDED CAPITAL PROJECTS
PROJECT NAME: South Ferran Parks Restroom
PROJECT DESCRIPTION AND JUSTIFICATION:
The South Ferran Park restroom is experiencing
structural issues due to water damage to the building's
framing. PW has recommended demolishing the building
and reconstructing it.
Site Development / Construction
TOTAL
PROJECT ADDITIONS / CHANGES
Unfunded
300,000
300,000