CIP 2027-2031 (Final) - Flipbook - Page 53
PROPOSED 5 YEAR CIP - 1ST READING
JULY 16, 2026
CITY OF EUSTIS
CAPITAL PROJECT REQUEST - FIVE YEAR CIP
>$25,000
FORM F-300 - PROJECTS
DEPT / FUND:
001 - General Fund
PROGRAM: 8600 - Projects
PROJECT NAME: P & R / Aquatics Center Splash Pad
PROJECT STATUS: Future year
ACCT1#:
ACCT2#:
ACCT3#:
PROJECT DESCRIPTION AND JUSTIFICATION:
ADDITIONS / CHANGES JUSTIFICATION
The splash pad has experienced wear and tear. In some
cases, this presents a safety issue. Some of the splash pad
needs to be replaced.
PURPOSE OF PROJECT:
X
Extend life of existing infrastructure
Capital improvements
Strategic plan /comp plan
Replace existing infrastructure
Expand infrastructure
ESTIMATED COST BY YEAR:
Curr. Year
FY 25/26
Land Acquisition
Planning
Design
Architecture/Engineering
Site Devel./Construction
Equipment
Contingency
Other
Project Additions/Changes
TOTAL
PRIORITY:
X Risk
Return on Investment
X Service Level Maint.
Service Level Impro
FY 26/27
-
FY 27/28
-
FY 28/29
-
FY 29/30
-
FY 30/31
-
5 YR TOTAL
50,000
50,000
-
50,000
50,000
Safety concern, hazardous condition, compliance, non-functional, etc
Highly visible, benefit outweighs cost, economic development potential
Maintains City desired level of service
New or improved service to meet demand
IMPACT ON ANNUAL
OPERATING BUDGET:
Curr. Year
Utility Costs
Maintenance Costs
PROPOSED FUNDING SOURCE(S):
1) 001 - General Fund
2)
3)
FY 26/27
FY 27/28
-
FY 28/29
-
FY 29/30
FY 30/31
5 YR TOTAL
STRATEGIC PRIORITY, if applicable
LOCATION:
Carver Park
POTENTIAL GRANT FUNDING SOURCE IF APPLICABLE: (List source and matching requirements)
PROJECT LEAD NAME & CONTACT INFO (ADDITIONAL PROJECT INFO AS NEEDED)
Sam Brinson - Parks Director
42 of 186
-