CIP Book FY 2023-27 - Final - Flipbook - Page 220
CITY OF EUSTIS
CAPITAL PROJECT/EQUIPMENT REQUEST - FIVE YEAR CIP (>$25,000)
FORM F-300
DEPARTMENT: Wastewater - 535
(1) PROJECT NAME: SEWER / BIOLOGICAL PROCESS EQUIPMENT
PROJECT STATUS: NEW Project This Year
PROGRAM:
Sewer Projects - 8600
ACCT1#:
042-8600-535-66-92
ACCT2#:
ACCT3#:
PROJECT ADDITIONS/CHANGES JUSTIFICATION:
(2) PROJECT DESCRIPTION AND JUSTIFICATION:
Mixers & Process Pumping Repair and Replacement. Mixers and Process Pumping are
require to maintain biological treatment. Equipment requires periodic reapair and maintenance, rebuilds, full replacement and minor modifications.
(3) PURPOSE OF PROJECT:
X
Extend life of existing infrastructure
X
Replace existing infrastructure
Expand infrastructure
X
Replace existing vehicles or equipment
Add new equipment or vehicles
Capital improvements
Strategic plan /comprehensive plan bonus
(4) ESTIMATED COST BY YEAR:
Current Year
21/22
a.
b.
c.
d.
e.
f.
g.
h.
i.
Land Acquisition
Planning
Design
Architecture/Engineering
Site Development/Construction
Equipment,Vehicles, Etc
Contingency
Other
Project Additions/Changes
TOTAL
(5) PRIORITY:
FY 22/23
FY 23/24
FY 24/25
FY 25/26
FY 26/27
TOTAL
-
56,000
26,000
26,000
26,000
26,000
-
56,000
26,000
26,000
26,000
26,000
Timetable
160,000
160,000
safety concern, hazardous condition, agency compliance, non-functional, etc
First Year
highly visible, benefit outweighs cost over short period, economic
b.
return on investment
development potential
1 - 3 Years out
c. X service level mainten.
maintains City desired level of service
2 - 5 Years out
d. X service level improvm.
new or improved service to meet demand
As Budget Allows
(6) EFFECTS ON ANNUAL OPERATING BUDGET:
Current Year
YEARS
21/22
FY 22/23
FY 23/24
FY 24/25
FY 25/26
FY26/27
2028-2032
TOTAL
Change in Fuel Costs
Change in Utility Costs
Change in Maintenance
Costs
(7) PROPOSED FUNDING SOURCE(S):
(9) PROJECT OR EQUIP LOCATION:
801 Bates Ave.
1) Water & Sewer R&R Fund 042
2)
3)
(7a) POTENTIAL GRANT FUNDING SOURCE IF APPLICABLE: (List source and matching requirements)
N/A
a.
risk
(8) PROJECT LEAD NAME & CONTACT INFO (ADDITIONAL PROJECT INFO AS NEEDED)
Greg Dobbins - Director of Utilities
218