CAPITAL PROJECT/EQUIPMENT REQUEST - FIVE YEAR CIP (>$25,000)
FORM F-300
DEPARTMENT: Public Utilities
(1) PROJECT NAME: PW UTILITIES / F-150 PICKUP TRUCK
PROJECT STATUS: Existing in Edmunds
PROGRAM:
Administration - 3100
ACCT1#:
040-3100-536-60-64
ACCT2#:
ACCT3#:
PROJECT ADDITIONS/CHANGES JUSTIFICATION:
(2) PROJECT DESCRIPTION AND JUSTIFICATION:
Replace Engineering Survey Vehicles
The cost has been moved from FY 27/28 to FY 26/27
(3) PURPOSE OF PROJECT:
Extend life of existing infrastructure
Replace existing infrastructure
Expand infrastructure
X
Replace existing vehicles or equipment
Add new equipment or vehicles
Capital improvements
Strategic plan /comprehensive plan bonus
(4) ESTIMATED COST BY YEAR:
Current Year
23/24
a.
b.
c.
d.
e.
f.
g.
h.
i.
Land Acquisition
Planning
Design
Architecture/Engineering
Site Development/Construction
Equipment,Vehicles, Etc
Contingency
Other
Project Additions/Changes
TOTAL
(5) PRIORITY:
FY 25/26
FY 24/25
FY 26/27
FY 27/28
FY 28/29
-
-
40,000
40,000
-
-
-
40,000
40,000
-
TOTAL
-
Timetable
80,000
80,000
safety concern, hazardous condition, agency compliance, non-functional, etc
First Year
highly visible, benefit outweighs cost over short period, economic
development potential
1 - 3 Years out
b.
return on investment
2 - 5 Years out
c.
service level mainten.
maintains City desired level of service
As Budget Allows
d.
service level improvm.
new or improved service to meet demand
(6) EFFECTS ON ANNUAL OPERATING BUDGET:
YEARS
Current Year
FY 25/26
FY 26/27
FY 27/28
FY28/29
2030-2034
TOTAL
23/24
FY 24/25
Change in Fuel Costs
Change in Utility Costs
Change in Maintenance
Costs
(7) PROPOSED FUNDING SOURCE(S):
(9) PROJECT OR EQUIP LOCATION:
City Hall
1) Water & Sewer Revenue Fund 040
2)
3)
(7a) POTENTIAL GRANT FUNDING SOURCE IF APPLICABLE: (List source and matching requirements)
a.
risk
(8) PROJECT LEAD NAME & CONTACT INFO (ADDITIONAL PROJECT INFO AS NEEDED)
Rick Gierok - Director of Public Works