(1) PROJECT NAME: PW FACILITIES / AMERICA IN BLOOM PROJECTS
PROJECT STATUS: NEW Project This Year
PROGRAM:
ACCT1#:
001-4930-517-60-63
ACCT2#:
013-4110-541-60-63
ACCT3#:
PROJECT ADDITIONS/CHANGES JUSTIFICATION:
(2) PROJECT DESCRIPTION AND JUSTIFICATION:
Provide funding for identified projects in accordance with America in Bloom. Next year, it
can be budgeted under the cemetery improvements. Subsequent years to be identified as
opportunities arise.
(3) PURPOSE OF PROJECT:
Extend life of existing infrastructure
Replace existing infrastructure
Expand infrastructure
Cemetery Maintenance - 4920
New project
X
Replace existing vehicles or equipment
Add new equipment or vehicles
Capital improvements
Strategic plan /comprehensive plan bonus
(4) ESTIMATED COST BY YEAR:
Current Year
23/24
a.
b.
c.
d.
e.
f.
g.
h.
i.
Land Acquisition
Planning
Design
Architecture/Engineering
Site Development/Construction
Equipment,Vehicles, Etc
Contingency
Other
Project Additions/Changes
TOTAL
(5) PRIORITY:
FY 24/25
FY 25/26
FY 26/27
FY 27/28
-
20,000
-
20,000
80,000
20,000
80,000
20,000
80,000
-
20,000
100,000
100,000
100,000
FY 28/29
TOTAL
20,000
80,000
100,000
Timetable
100,000
320,000
420,000
safety concern, hazardous condition, agency compliance, non-functional, etc
First Year
highly visible, benefit outweighs cost over short period, economic
development potential
1 - 3 Years out
b.
return on investment
2 - 5 Years out
c.
service level mainten.
maintains City desired level of service
As Budget Allows
d. x service level improvm.
new or improved service to meet demand
(6) EFFECTS ON ANNUAL OPERATING BUDGET:
YEARS
Current Year
FY 25/26
FY 26/27
FY 27/28
FY28/29
2030-2034
TOTAL
FY 24/25
23/24
Change in Fuel Costs
Change in Utility Costs
Change in Maintenance
Costs
(7) PROPOSED FUNDING SOURCE(S):
(9) PROJECT OR EQUIP LOCATION:
1) General Fund 001
2) Street Improvement Fund 013
3)
(7a) POTENTIAL GRANT FUNDING SOURCE IF APPLICABLE: (List source and matching requirements)
a.
risk
(8) PROJECT LEAD NAME & CONTACT INFO (ADDITIONAL PROJECT INFO AS NEEDED)
Rick Gierok - Director of Public Works
139