CIP - FY 2025-29 FINAL - Flipbook - Page 219
Capital Improvement Plan
CITY OF EUSTIS
CAPITAL PROJECT/EQUIPMENT REQUEST - FIVE YEAR CIP (>$25,000)
FORM F-300
DEPARTMENT: Water
PROGRAM: Water Capital Projects - 8600
(1) PROJECT NAME: WATER / LAUREL OAK RD. WATER MAIN REPLACEMENT
PROJECT STATUS: Existing in Edmunds
ACCT1#:
042-8600-533-65-81
ACCT2#:
ACCT3#:
(2) PROJECT DESCRIPTION AND JUSTIFICATION:
PROJECT ADDITIONS/CHANGES JUSTIFICATION:
Increased cost of engineering to include survey 2024.
This project will replace 600 feet of 2” galvanized water main with 6” PVC. The construction will be open trench. This project will include the installation of fire hydrants and will
require re-establishment of the road. The project will increase flow and water quality, while
adding fire protection. $50K engineering fees, construction is in 28/29.
(3) PURPOSE OF PROJECT:
Extend life of existing infrastructure
X
Replace existing infrastructure
Expand infrastructure
Replace existing vehicles or equipment
Add new equipment or vehicles
Capital improvements
Strategic plan /comprehensive plan bonus
(4) ESTIMATED COST BY YEAR:
Current Year
23/24
a.
b.
c.
d.
e.
f.
g.
h.
i.
Land Acquisition
Planning
Design
Architecture/Engineering
Site Development/Construction
Equipment,Vehicles, Etc
Contingency
Other
Project Additions/Changes
TOTAL
(5) PRIORITY:
FY 25/26
FY 24/25
FY 26/27
FY 27/28
FY 28/29
-
-
-
50,000
-
-
-
-
-
-
-
-
-
50,000
100,000
-
TOTAL
50,000
300,000
300,000
50,000
300,000
400,000
Timetable
safety concern, hazardous condition, agency compliance, non-functional, etc
First Year
highly visible, benefit outweighs cost over short period, economic
development potential
1 - 3 Years out
b.
return on investment
2 - 5 Years out
c. X service level mainten.
maintains City desired level of service
As Budget Allows
d.
service level improvm.
new or improved service to meet demand
(6) EFFECTS ON ANNUAL OPERATING BUDGET:
YEARS
Current Year
FY 25/26
FY 26/27
FY 27/28
FY28/29
2030-2034
TOTAL
FY 24/25
23/24
Change in Fuel Costs
Change in Utility Costs
Change in Maintenance
Costs
(7) PROPOSED FUNDING SOURCE(S):
(9) PROJECT OR EQUIP LOCATION:
Laurel Oak Rd.
1) Water & Sewer R&R Fund 042
2)
3)
(7a) POTENTIAL GRANT FUNDING SOURCE IF APPLICABLE: (List source and matching requirements)
N/A
a.
risk
(8) PROJECT LEAD NAME & CONTACT INFO (ADDITIONAL PROJECT INFO AS NEEDED)
Greg Dobbins - Director of Utilities
207