CAPITAL PROJECT/EQUIPMENT REQUEST - FIVE YEAR CIP (>$25,000)
FORM F-300
DEPARTMENT: Water
(1) PROJECT NAME: WATER IMPACT / ROSENWALD 7 BLOCK WATERMAIN
PROJECT STATUS: NEW Project This Year
ACCT1#:
065-8600-533-67-16
ACCT2#:
ACCT3#:
PROJECT ADDITIONS/CHANGES JUSTIFICATION:
(2) PROJECT DESCRIPTION AND JUSTIFICATION:
Install a looped water main down each of the 7 blocks of the Rosenwald area from Wall St
tieing in to the new Coolidge utility line. An additional project was added for the sewer
installation additionally. The construction costs for this project are estimated at $50,000 per
block.
(3) PURPOSE OF PROJECT:
Extend life of existing infrastructure
Replace existing infrastructure
x
Expand infrastructure
Water Impact Projects - 8600
PROGRAM:
new project
x
Replace existing vehicles or equipment
Add new equipment or vehicles
Capital improvements
Strategic plan /comprehensive plan bonus
(4) ESTIMATED COST BY YEAR:
Current Year
23/24
a.
b.
c.
d.
e.
f.
g.
h.
i.
Land Acquisition
Planning
Design
Architecture/Engineering
Site Development/Construction
Equipment,Vehicles, Etc
Contingency
Other
Project Additions/Changes
TOTAL
(5) PRIORITY:
FY 24/25
FY 25/26
FY 26/27
FY 27/28
FY 28/29
-
50,000
100,000
250,000
-
-
-
150,000
250,000
-
-
TOTAL
50,000
350,000
400,000
Timetable
safety concern, hazardous condition, agency compliance, non-functional, etc
First Year
highly visible, benefit outweighs cost over short period, economic
development potential
1 - 3 Years out
b.
return on investment
2 - 5 Years out
c.
service level mainten.
maintains City desired level of service
As Budget Allows
d.
service level improvm.
new or improved service to meet demand
(6) EFFECTS ON ANNUAL OPERATING BUDGET:
YEARS
Current Year
FY 25/26
FY 26/27
FY 27/28
FY28/29
2030-2034
TOTAL
FY 24/25
23/24
Change in Fuel Costs
Change in Utility Costs
Change in Maintenance
Costs
(7) PROPOSED FUNDING SOURCE(S):
(9) PROJECT OR EQUIP LOCATION:
1) Water Impact Fee Fund 065
2)
3)
(7a) POTENTIAL GRANT FUNDING SOURCE IF APPLICABLE: (List source and matching requirements)
a.
risk
(8) PROJECT LEAD NAME & CONTACT INFO (ADDITIONAL PROJECT INFO AS NEEDED)
Rick Gierok - Director of Public Works