Capital Improvement Plan
CITY OF EUSTIS
CAPITAL PROJECT/EQUIPMENT REQUEST - FIVE YEAR CIP (>$25,000)
FORM F-300
DEPARTMENT: Fire
(1) PROJECT NAME:
PROJECT STATUS:
PROGRAM:
FIRE / ANNUAL RADIO PAYMENT
Existing in Edmunds
Fire Capital -8600
ACCT1#:
010-8600-522-60-17
ACCT2#:
ACCT3#:
PROJECT ADDITIONS/CHANGES JUSTIFICATION:
(2) PROJECT DESCRIPTION AND JUSTIFICATION:
Annual Radio Payment combined with EPD
.
(3) PURPOSE OF PROJECT:
Extend life of existing infrastructure
Replace existing infrastructure
Expand infrastructure
x
Replace existing vehicles or equipment
Add new equipment or vehicles
Capital improvements
Strategic plan /comprehensive plan bonus
(4) ESTIMATED COST BY YEAR:
Current Year
23/24
a.
b.
c.
d.
e.
f.
g.
h.
i.
Land Acquisition
Planning
Design
Architecture/Engineering
Site Development/Construction
Equipment,Vehicles, Etc
Contingency
Other
Project Additions/Changes
TOTAL
(5) PRIORITY:
FY 24/25
FY 25/26
FY 26/27
FY 27/28
55,000
55,000
55,000
55,000
55,000
55,000
55,000
55,000
55,000
55,000
FY 28/29
TOTAL
Timetable
275,000
275,000
safety concern, hazardous condition, agency compliance, non-functional, etc
First Year
highly visible, benefit outweighs cost over short period, economic
development potential
1 - 3 Years out
b.
return on investment
2 - 5 Years out
c.
service level mainten.
maintains City desired level of service
As Budget Allows
d.
service level improvm.
new or improved service to meet demand
(6) EFFECTS ON ANNUAL OPERATING BUDGET:
YEARS
Current Year
FY 25/26
FY 26/27
FY 27/28
FY28/29
2030-2034
TOTAL
23/24
FY 24/25
Change in Fuel Costs
Change in Utility Costs
Change in Maintenance
Costs
(7) PROPOSED FUNDING SOURCE(S):
(9) PROJECT OR EQUIP LOCATION:
1) Sales Tax Capital Project Fund 010
2)
3)
(7a) POTENTIAL GRANT FUNDING SOURCE IF APPLICABLE: (List source and matching requirements)
a.
risk
(8) PROJECT LEAD NAME & CONTACT INFO (ADDITIONAL PROJECT INFO AS NEEDED)
Mike Swanson – Fire Chief